network chart,software project management,schedule planning,critical path method,gantt chart,"/> 基于网络图的软件项目进度计划编制

J4 ›› 2011, Vol. 29 ›› Issue (02): 128-.

• 论文 • 上一篇    下一篇

基于网络图的软件项目进度计划编制

任永昌1|邢 涛2|刘大成3   

  1. 1渤海大学 信息科学与技术学院|辽宁 锦州 121013;2北京城市系统工程研究中心|北京 100089;3清华大学 工业工程系|北京 100084
  • 出版日期:2011-03-25 发布日期:2011-04-25
  • 通讯作者: 任永昌(1969— ),男,辽宁喀左人,渤海大学副教授,硕士生导师,主要从事软件项目管理研究,(Tel)86-13897854226 E-mail:rycryc@sina.com。
  • 作者简介:任永昌(1969— )|男|辽宁喀左人|渤海大学副教授|硕士生导师|主要从事软件项目管理研究|(Tel)86-13897854226(E-mail)rycryc@sina.com。
  • 基金资助:

    国家自然科学基金资助项目(70871067);国家863计划基金资助项目(2005AA501560);辽宁省博士基金资助项目(20091034)

Schedule Planning of Software Project Based on Network Chart

REN Yong-chang| XING Tao| LIU Da-cheng   

  1. 1College of Information Science and Technology, Bohai University, Jinzhou 121013, China; 2 Beijing Research Center of Urban Systems Engineering, Beijing 100089, China;3Department of Industrial Engineering, Tsinghua University, Beijing 100084, China
  • Online:2011-03-25 Published:2011-04-25

摘要:

制订周密、简洁和精确的软件项目进度计划,是软件项目开发成功的关键。针对当前进度计划主要采用手工方法,编制速度慢、缺乏科学性等特点,基于网络图,运用工作分解结构、计划评审技术、关键路径法、甘特图等技术对其进行研究。说明了前期准备工作,包括定义活动、活动排序、绘制网络图;给出了推导时间参数公式,包括活动时间估计、项目周期估计、活动时间计算;并通过实例阐述了编制过程。结果表明,该方法对软件项目进度计划编制具有较高的实用价值。

关键词: 网络图, 软件项目管理, 进度计划, 关键路径法, 甘特图

Abstract:

Well-developed, concise and accurate software project schedule planning is the key to successful software development.The current schedule planning mainly uses manual methods, draw up slow, lack of scientific characteristics and so on, the article bases on the network chart, the use of work breakdown structures, program evaluation and review technique, critical path method, gantt chart and other technical studies. It illustrates preparatory work firstly, including the definition of activities, activity sequencing, drawing the network chart, gives time parameters derived formula, including estimation the activity time, estimation the project cycle, calculation activity time, and describes preparation process by examples. The results show that the method of software project scheduling planning has high practical value.

Key words: network chart')">

network chart, software project management, schedule planning, critical path method, gantt chart